Update On Second Niger Bridge: Only 4km Approach Road From Asaba Left
This is the correct UPDATE on 2nd Niger Bridge:
The Project is 3 main components:
– 1.6km Bridge – completed ✅
– ~7km Approach Road (6-lane) on Onitsha side; ~5km completed.
– ~4km Approach Road (6-L) on Asaba side – construction just about to start, delayed now by flooding.
This is the correct UPDATE on 2nd Niger Bridge:
The Project is 3 main components:
– 1.6km Bridge – completed ✅
– ~7km Approach Road (6-lane) on Onitsha side; ~5km completed.
– ~4km Approach Road (6-L) on Asaba side – construction just about to start, delayed now by flooding. pic.twitter.com/WAzyUq37tz
— Tolu Ogunlesi, MON (@toluogunlesi) October 19, 2022