FG Releases ₦2.5 Billion For Deplorable Eleme-One Section Of East West Road
The Federal Government has released the sum of N2.5 billion for compensation to pave ways for remedial works to be carried out on the deplorable Eleme-One Section of the East West road.
The Minister of Niger Delta Affairs, Senator Godswill Akpabio, who made this known after a meeting with the management of RCC, the construction firm handling the projects directed the firm to start work by Friday.
He, therefore, appealed to protesting Niger Delta youths to vacate section 3 of the East-West road to enable contractors commence work.
According to him, “The essence of this protest is to draw the attention of the government to the road, now we are here allow us to commence work.”
Akpabio acknowledged that the youths were right to stage a protest over the delay.
The Minister who disclosed that the federal government has released additional N2.5 billion for payment of compensation to property owners along the road corridor regretted that the initial N4.5 billion budgeted for compensation could not meet up with demands.
He disclosed that the Niger Delta Development Commission (NDDC) has also budgeted another N35 billion to support the project, adding that the ministry has channeled funds met for over 304 projects into the East-West road project.
He further disclosed that the Ministry has proposed an extra-budgetary intervention for inclusion of the East-West Road Sections I-IV in the 2020 SUKUK Issuance Programme of the Ministry of Finance, Budget and National Planning and the Debt Management Office.
This according to him is part of the efforts made by the Ministry to access adequate funding for the completion of the East-West road project.
The Minister explained that the initial contracts for dualization of the 338km road linking Warri to Oron through Kaima, Ahoada, Port Harcourt, Ogoni and Eket Townships (Section I-IV) was initially awarded in four sections to four different contractors in 2006.
“It is well known that Section I (Warri-Kaima covering Ch. 0+000-Ch. 87+400 and Section III) and Section III (Onne Port Junction – Eket covering Ch. 15 + 000 – Ch. 99 + 000) have been duly completed by Messrs Setraco Nigeria Limited and Messrs. RCC Nigeria Limited respectively” he added.
He maintained that the section IIIA (Port Harcourt Onne Road Junction, covering Ch. 0 + 000 – Ch. 15 + 000 was not part of the contract initially awarded in 2006 because it was in good condition having been dualized earlier, noting that “over time, the Port Harcourt – Onne Port Junction portion had progressively deteriorated as a result of heavy axle loading, flooding and is no longer serviceable for the current traffic volumes.
FG Releases ₦2.5 Billion For Deplorable Eleme-One Section Of East West Road
”Therefore, the Ministry had to award the contract for additional works to Messrs RCC Nigeria Limited to upgrade the Port Harcourt Onne Port Junction”.
He further stated that due to poor annual budgetary provisions, the contract for upgrading of Section IIIA awarded in 2014 could not commence until the Ministry paid the contractors the full mobilization Advance in 2020.
“The condition of the road deteriorated during the period of delay and there has been serious encroachment on the right-of-way initially delineated for the road.
“With the review of the initial contract scope of works and contract unit rates imperative, specific measures for addressing the contingent site conditions militating against the progress of work were scheduled by the Ministry.
He said these include the initial design for interchange bridges at Onne Junction which is to be substituted with a flyover bridge, but due to space constraints caused by the newly constructed Power Sub-Station which cannot be relocated due to higher cost implication.
“A new flyover bridge has also been designed to replace the interchange bridge initially designed for Refinery Junction amongst others.”
The minister further reiterated the commitment of the present administration led by President Muhammadu Buhari to complete the East West highway dualisation project by 2022.